Performing a rate analysis for Plain Cement Concrete (PCC) with a mix ratio of 1:4:8 (M7.5) involves calculating the quantities and costs of materials, labor, and other associated expenses for 1 cubic meter (m³) of concrete. Here's a step-by-step breakdown:

  • Calculate Dry Volume
  • Concrete ingredients are measured in dry volume.
  • Dry Volume = Wet Volume × 1.54
  • For 1 m³ of PCC:

    • Dry Volume = 1 m³ × 1.54 = 1.54 m³
  • Material Quantities

  • Mix Ratio: 1 (Cement): 4 (Sand): 8 (Aggregate)
  • Total Parts: 1 + 4 + 8 = 13

  • Cement:

    • Volume = (1/13) × 1.54 m³ = 0.118 m³
    • Density of Cement = 1,440 kg/m³
    • Weight = 0.118 m³ × 1,440 kg/m³ = 170 kg
    • Bags (50 kg each) = 170 kg / 50 kg = 3.4 bags
  • Sand:

    • Volume = (4/13) × 1.54 m³ = 0.474 m³
    • 1 m³ = 35.32 cubic feet (cft)
    • Volume in cft = 0.474 m³ × 35.32 cft/m³ = 16.73 cft
  • Aggregate:

    • Volume = (8/13) × 1.54 m³ = 0.948 m³
    • Volume in cft = 0.948 m³ × 35.32 cft/m³ = 33.47 cft
  • Material Costs

  • Cement:

    • Cost per Bag =400
    • Total Cost = 3.4 bags ×400/bag = ?1,360
  • Sand:

    • Cost per cft =60
    • Total Cost = 16.73 cft ×60/cft = ?1,003.8
  • Aggregate:

    • Cost per cft =60
    • Total Cost = 33.47 cft ×60/cft = ?2,008.2
  • Total Material Cost:

    • ?1,360 +1,003.8 +2,008.2 = ?4,372
  • Labor Costs

  • For 1 m³ of PCC:

    • Labor Rate =850/m³
    • Total Labor Cost = ?850
  • Additional Expenses

  • Water Charges:

    • Assume 1.5% of Material Cost
    • ?4,372 × 1.5% = ?65.58
  • Overhead Expenses:

    • Assume 2% of Material Cost
    • ?4,372 × 2% = ?87.44
  • Equipment and Tools:

    • Assume 1.5% of Material Cost
    • ?4,372 × 1.5% = ?65.58
  • Contractor Profit:

    • Assume 10% of Material Cost
    • ?4,372 × 10% = ?437.2
  • Total Cost

  • Material Cost:4,372
  • Labor Cost:850
  • Water Charges:65.58
  • Overhead Expenses:87.44
  • Equipment and Tools:65.58
  • Contractor Profit:437.2
  • Total Cost:
    • ?4,372 +850 +65.58 +87.44 +65.58 +437.2 = ?5,878.8

Therefore, the estimated cost for 1 cubic meter of PCC 1:4:8 (M7.5) is approximately ?5,879.

Note: Costs can vary based on local rates and market conditions. It's advisable to obtain current prices for accurate estimations.


Next: Read 2500+ consumer guides to shopping, electronics, appliances, home services, cars, money and more.
If you liked all this, consider supporting us by checking out Tiny Skills - 250+ Top Work & Personal Skills Made Easy

The Success Manuals


The Career Advice Bible

100+ Most Important Career Questions
Finally Answered

318 Pages | $5 | PDF & EPub, Kindle Ready

250 Top Work & Personal Skills Made Easy

The First & Only Encyclopedia of Self Help,
Self Improvement & Career Advice

250+ Easy-to-Follow Guides
5000+ Proven Tips

13 Types of Essential Skills Covered
Get The Value of 100+ Best Books in 1 Book.

502 Pages | $5 | PDF / EPub, Kindle Ready