Rate Analysis For Pcc 1:4:8 (M7.5) – Calculate Quantity & Cost

On February 25, 2026  By newsroom   Topic: India Home Advice

Performing a rate analysis for Plain Cement Concrete (PCC) with a mix ratio of 1:4:8 (M7.5) involves calculating the quantities and costs of materials, labor, and other associated expenses for 1 cubic meter (m³) of concrete. Here's a step-by-step breakdown:

  • Calculate Dry Volume
  • Concrete ingredients are measured in dry volume.
  • Dry Volume = Wet Volume × 1.54
  • For 1 m³ of PCC:

    • Dry Volume = 1 m³ × 1.54 = 1.54 m³
  • Material Quantities

  • Mix Ratio: 1 (Cement): 4 (Sand): 8 (Aggregate)
  • Total Parts: 1 + 4 + 8 = 13

  • Cement:

    • Volume = (1/13) × 1.54 m³ = 0.118 m³
    • Density of Cement = 1,440 kg/m³
    • Weight = 0.118 m³ × 1,440 kg/m³ = 170 kg
    • Bags (50 kg each) = 170 kg / 50 kg = 3.4 bags
  • Sand:

    • Volume = (4/13) × 1.54 m³ = 0.474 m³
    • 1 m³ = 35.32 cubic feet (cft)
    • Volume in cft = 0.474 m³ × 35.32 cft/m³ = 16.73 cft
  • Aggregate:

    • Volume = (8/13) × 1.54 m³ = 0.948 m³
    • Volume in cft = 0.948 m³ × 35.32 cft/m³ = 33.47 cft
  • Material Costs

  • Cement:

    • Cost per Bag =400
    • Total Cost = 3.4 bags ×400/bag = ?1,360
  • Sand:

    • Cost per cft =60
    • Total Cost = 16.73 cft ×60/cft = ?1,003.8
  • Aggregate:

    • Cost per cft =60
    • Total Cost = 33.47 cft ×60/cft = ?2,008.2
  • Total Material Cost:

    • ?1,360 +1,003.8 +2,008.2 = ?4,372
  • Labor Costs

  • For 1 m³ of PCC:

    • Labor Rate =850/m³
    • Total Labor Cost = ?850
  • Additional Expenses

  • Water Charges:

    • Assume 1.5% of Material Cost
    • ?4,372 × 1.5% = ?65.58
  • Overhead Expenses:

    • Assume 2% of Material Cost
    • ?4,372 × 2% = ?87.44
  • Equipment and Tools:

    • Assume 1.5% of Material Cost
    • ?4,372 × 1.5% = ?65.58
  • Contractor Profit:

    • Assume 10% of Material Cost
    • ?4,372 × 10% = ?437.2
  • Total Cost

  • Material Cost:4,372
  • Labor Cost:850
  • Water Charges:65.58
  • Overhead Expenses:87.44
  • Equipment and Tools:65.58
  • Contractor Profit:437.2
  • Total Cost:
    • ?4,372 +850 +65.58 +87.44 +65.58 +437.2 = ?5,878.8

Therefore, the estimated cost for 1 cubic meter of PCC 1:4:8 (M7.5) is approximately ?5,879.

Note: Costs can vary based on local rates and market conditions. It's advisable to obtain current prices for accurate estimations.


Next: Read 2500+ consumer guides to shopping, electronics, appliances, home services, cars, money and more.
If you liked all this, consider supporting us by checking out SkillThing DOING Manuals

DOING Manuals


The AI Proof Career

Future-proof your work in the AI age.


31 Days to Escaping Job Search Hell

Escape job search hell right out of college. Get job-ready in 31 days.