1. Wall Putty
-
Coverage: Approximately 12-15 sq ft per kg for two coats.
-
Calculation:
-
For 2,000 sq ft:
- Minimum: 2,000 sq ft ÷ 15 sq ft/kg 133 kg
- Maximum: 2,000 sq ft ÷ 12 sq ft/kg 167 kg
-
Bags Required:
-
Assuming 40 kg per bag:
- Minimum: 133 kg ÷ 40 kg/bag 3.33 bags
- Maximum: 167 kg ÷ 40 kg/bag 4.18 bags
-
Cost Estimate:
-
If one bag costs800:
- Minimum: 4 bags ×800 =3,200
- Maximum: 5 bags ×800 =4,000
-
Labor Cost:
- Approximately3 per sq ft for two coats.
-
Total: 2,000 sq ft ×3 =6,000
-
Total Putty Application Cost:
- Minimum:3,200 (material) +6,000 (labor) =9,200
- Maximum:4,000 (material) +6,000 (labor) =10,000
2. Primer
-
Coverage: Approximately 120-140 sq ft per liter for one coat.
-
Calculation:
-
For 2,000 sq ft:
- Minimum: 2,000 sq ft ÷ 140 sq ft/liter 14.3 liters
- Maximum: 2,000 sq ft ÷ 120 sq ft/liter 16.7 liters
-
Cost Estimate:
-
If one liter costs200:
- Minimum: 15 liters ×200 =3,000
- Maximum: 17 liters ×200 =3,400
-
Labor Cost:
- Approximately2 per sq ft for one coat.
-
Total: 2,000 sq ft ×2 =4,000
-
Total Primer Application Cost:
- Minimum:3,000 (material) +4,000 (labor) =7,000
- Maximum:3,400 (material) +4,000 (labor) =7,400
3. Paint
-
Coverage: Approximately 100-120 sq ft per liter for one coat.
-
Calculation:
-
For two coats over 2,000 sq ft:
- Total Area: 2,000 sq ft × 2 = 4,000 sq ft
- Minimum: 4,000 sq ft ÷ 120 sq ft/liter 33.3 liters
- Maximum: 4,000 sq ft ÷ 100 sq ft/liter 40 liters
-
Cost Estimate:
-
If one liter costs300:
- Minimum: 34 liters ×300 =10,200
- Maximum: 40 liters ×300 =12,000
-
Labor Cost:
- Approximately6 per sq ft for two coats.
-
Total: 2,000 sq ft ×6 =12,000
-
Total Paint Application Cost:
- Minimum:10,200 (material) +12,000 (labor) =22,200
- Maximum:12,000 (material) +12,000 (labor) =24,000
4. Summary
- Wall Putty:
- Material:3,200 -4,000
- Labor:6,000
-
Total:9,200 -10,000
-
Primer:
- Material:3,000 -3,400
- Labor:4,000
-
Total:7,000 -7,400
-
Paint:
- Material:10,200 -12,000
- Labor:12,000
-
Total:22,200 -24,000
-
Grand Total:
- Minimum:9,200 +7,000 +22,200 =38,400